3-4-04


Dorsett Bros.
Concrete is proud to be the Concrete supplier for the new
Galveston Causeway Project with Traylor Bros. Much thought went
into the capability of supplying this material. The result, a
very well thought out complete central-mix plant erected on a
Traylor Bros. Barge. The above upper photo shows the complete
plant. The construction of the plant on the barge took two
months to complete. The following is a break-down of the plant:
(1) A Vince Hagan Batch Plant with a 10 yard
Horizontal Mixer
(2) A 600 Linkbelt Modified Excavator with a 2 1/2 yard
hydraulic claim bucket used for transferring material to the
plant.
(3) A complete pump and boom that can extend tall enough and far
enough, to supply concrete to all required areas.
(4) A 550 1000 Amp Genset Generator supplies all the power to
make the plant fully functional.
(5) Admix tanks and also a water chiller for temperature
controlled concrete
The above lower
photo is of barges that are capable of bringing all materials
needed directly to the plant. This enables the plant to stay in
position without having to re-dock for material supply.
Details From: BJ Dorsett